AUSTIN · PERMIT TIMELINES

How long does a addition permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

60 calendar days

n = 468 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 468. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-064092 BP787312026-03-312026-05-21512026
2026-125146 BP787262026-09-072026-09-24172026
2026-012063 BP787592025-12-042026-02-17752026
2004-006956 BP787462004-02-012025-11-0479472025
2026-023977 BP787392026-02-022026-02-26242026
2025-146440 BP787222025-10-012025-12-10702025
2025-133361 BP787022025-08-052025-11-11982025
2026-127179 BP787232026-08-302026-09-28292026
2026-038567 BP787442026-03-302026-03-3002026
2026-038143 BP787592025-12-282026-03-30922026
2025-022130 BP787032024-12-252025-12-023422025
2026-009495 BP787442026-01-252026-01-2502026
2025-160306 BP787392025-08-122026-01-111522026
2026-054590 BP787212025-11-062026-05-272022026
2026-025792 BP787362025-11-122026-03-151232026
2026-114689 BP787272026-06-212026-09-16872026
2025-148618 BP787592025-10-132025-11-19372025
2026-031552 BP787592026-03-052026-07-221392026
2025-138623 BP786172025-10-262025-11-0492025
2025-105445 BP787592025-06-172025-12-021682025
2026-114851 BP787412026-08-192026-09-01132026
2026-135655 BP787482026-05-042026-10-211702026
2026-131436 BP787352026-04-122026-10-131842026
2026-055759 BP787592026-02-162026-05-05782026
2026-020996 BP787042025-05-262026-03-032812026
2026-012749 BP787392025-12-012026-02-10712026
2026-017180 BP787302026-01-222026-02-16252026
2026-119694 BP787502026-09-012026-09-14132026
2026-013732 BP787502025-11-122026-02-04842026
2026-051226 BP787442026-04-232026-05-10172026
2026-115920 BP787582026-07-082026-09-16702026
2026-038524 BP787442026-03-302026-03-3002026
2026-125685 BP787582026-08-092026-10-06582026
2026-044136 BP787452026-04-092026-04-0902026
2026-035900 BP787592026-02-172026-03-24352026
2026-088174 BP787272026-04-282026-07-12752026
2026-037303 BP787352026-02-172026-03-31422026
2026-080970 BP787242026-06-232026-06-2302026
2025-157183 BP787532025-12-102025-12-1002025
2026-037336 BP787032026-02-222026-03-30362026
2025-147837 BP787172025-09-152025-11-24702025
2026-081780 BP787042026-05-192026-06-28402026
2026-057290 BP787212026-05-062026-05-17112026
2026-087149 BP787022026-03-162026-08-051422026
2026-048856 BP787042025-10-152026-07-202782026
2026-097678 BP787312026-05-272026-08-12772026
2026-109847 BP787312026-05-192026-08-20932026
2026-102061 BP787452026-07-062026-08-09342026
2026-088362 BP787592026-04-162026-07-10852026
2025-131979 BP787022024-04-282025-12-216022025

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.