AUSTIN · PERMIT TIMELINES
How long does a addition permit take in Austin?
Median application-to-issuance time
60 calendar days
n = 468 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.
Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.
Explore the ZIP-level record
Records used in this calculation
Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 468. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.
| Permit | ZIP | Applied | Issued | Calendar days | Source year |
|---|---|---|---|---|---|
| 2026-064092 BP | 78731 | 2026-03-31 | 2026-05-21 | 51 | 2026 |
| 2026-125146 BP | 78726 | 2026-09-07 | 2026-09-24 | 17 | 2026 |
| 2026-012063 BP | 78759 | 2025-12-04 | 2026-02-17 | 75 | 2026 |
| 2004-006956 BP | 78746 | 2004-02-01 | 2025-11-04 | 7947 | 2025 |
| 2026-023977 BP | 78739 | 2026-02-02 | 2026-02-26 | 24 | 2026 |
| 2025-146440 BP | 78722 | 2025-10-01 | 2025-12-10 | 70 | 2025 |
| 2025-133361 BP | 78702 | 2025-08-05 | 2025-11-11 | 98 | 2025 |
| 2026-127179 BP | 78723 | 2026-08-30 | 2026-09-28 | 29 | 2026 |
| 2026-038567 BP | 78744 | 2026-03-30 | 2026-03-30 | 0 | 2026 |
| 2026-038143 BP | 78759 | 2025-12-28 | 2026-03-30 | 92 | 2026 |
| 2025-022130 BP | 78703 | 2024-12-25 | 2025-12-02 | 342 | 2025 |
| 2026-009495 BP | 78744 | 2026-01-25 | 2026-01-25 | 0 | 2026 |
| 2025-160306 BP | 78739 | 2025-08-12 | 2026-01-11 | 152 | 2026 |
| 2026-054590 BP | 78721 | 2025-11-06 | 2026-05-27 | 202 | 2026 |
| 2026-025792 BP | 78736 | 2025-11-12 | 2026-03-15 | 123 | 2026 |
| 2026-114689 BP | 78727 | 2026-06-21 | 2026-09-16 | 87 | 2026 |
| 2025-148618 BP | 78759 | 2025-10-13 | 2025-11-19 | 37 | 2025 |
| 2026-031552 BP | 78759 | 2026-03-05 | 2026-07-22 | 139 | 2026 |
| 2025-138623 BP | 78617 | 2025-10-26 | 2025-11-04 | 9 | 2025 |
| 2025-105445 BP | 78759 | 2025-06-17 | 2025-12-02 | 168 | 2025 |
| 2026-114851 BP | 78741 | 2026-08-19 | 2026-09-01 | 13 | 2026 |
| 2026-135655 BP | 78748 | 2026-05-04 | 2026-10-21 | 170 | 2026 |
| 2026-131436 BP | 78735 | 2026-04-12 | 2026-10-13 | 184 | 2026 |
| 2026-055759 BP | 78759 | 2026-02-16 | 2026-05-05 | 78 | 2026 |
| 2026-020996 BP | 78704 | 2025-05-26 | 2026-03-03 | 281 | 2026 |
| 2026-012749 BP | 78739 | 2025-12-01 | 2026-02-10 | 71 | 2026 |
| 2026-017180 BP | 78730 | 2026-01-22 | 2026-02-16 | 25 | 2026 |
| 2026-119694 BP | 78750 | 2026-09-01 | 2026-09-14 | 13 | 2026 |
| 2026-013732 BP | 78750 | 2025-11-12 | 2026-02-04 | 84 | 2026 |
| 2026-051226 BP | 78744 | 2026-04-23 | 2026-05-10 | 17 | 2026 |
| 2026-115920 BP | 78758 | 2026-07-08 | 2026-09-16 | 70 | 2026 |
| 2026-038524 BP | 78744 | 2026-03-30 | 2026-03-30 | 0 | 2026 |
| 2026-125685 BP | 78758 | 2026-08-09 | 2026-10-06 | 58 | 2026 |
| 2026-044136 BP | 78745 | 2026-04-09 | 2026-04-09 | 0 | 2026 |
| 2026-035900 BP | 78759 | 2026-02-17 | 2026-03-24 | 35 | 2026 |
| 2026-088174 BP | 78727 | 2026-04-28 | 2026-07-12 | 75 | 2026 |
| 2026-037303 BP | 78735 | 2026-02-17 | 2026-03-31 | 42 | 2026 |
| 2026-080970 BP | 78724 | 2026-06-23 | 2026-06-23 | 0 | 2026 |
| 2025-157183 BP | 78753 | 2025-12-10 | 2025-12-10 | 0 | 2025 |
| 2026-037336 BP | 78703 | 2026-02-22 | 2026-03-30 | 36 | 2026 |
| 2025-147837 BP | 78717 | 2025-09-15 | 2025-11-24 | 70 | 2025 |
| 2026-081780 BP | 78704 | 2026-05-19 | 2026-06-28 | 40 | 2026 |
| 2026-057290 BP | 78721 | 2026-05-06 | 2026-05-17 | 11 | 2026 |
| 2026-087149 BP | 78702 | 2026-03-16 | 2026-08-05 | 142 | 2026 |
| 2026-048856 BP | 78704 | 2025-10-15 | 2026-07-20 | 278 | 2026 |
| 2026-097678 BP | 78731 | 2026-05-27 | 2026-08-12 | 77 | 2026 |
| 2026-109847 BP | 78731 | 2026-05-19 | 2026-08-20 | 93 | 2026 |
| 2026-102061 BP | 78745 | 2026-07-06 | 2026-08-09 | 34 | 2026 |
| 2026-088362 BP | 78759 | 2026-04-16 | 2026-07-10 | 85 | 2026 |
| 2025-131979 BP | 78702 | 2024-04-28 | 2025-12-21 | 602 | 2025 |
PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.