AUSTIN · PERMIT TIMELINES

How long does a bathroom remodel permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

53 calendar days

n = 425 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 425. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-084922 BP787232026-05-312026-07-06362026
2026-044642 BP787452026-04-122026-04-1532026
2026-106610 BP787572026-08-132026-08-1302026
2026-123601 BP787522026-09-012026-09-22212026
2026-093994 BP787212026-05-032026-07-21792026
2025-163602 BP787562025-10-202026-06-212442026
2026-094495 BP787352025-08-142026-08-033542026
2026-128574 BP787452026-07-292026-09-30632026
2026-057828 BP787032026-03-162026-05-18632026
2026-134629 BP787462025-06-152026-10-154872026
2026-009986 BP787452026-01-262026-01-2712026
2026-005376 BP787232025-12-222026-06-161762026
2026-084274 BP787042026-04-292026-08-03962026
2026-015881 BP787592026-02-092026-03-02212026
2026-124860 BP787462026-04-152026-09-231612026
2026-058038 BP787022026-04-072026-05-07302026
2026-043626 BP787222026-03-042026-09-282082026
2026-047480 BP787042025-11-052026-06-252322026
2026-060723 BP787452026-03-182026-07-211252026
2026-139476 BP787522026-08-092026-10-25772026
2026-069459 BP787452026-03-112026-06-09902026
2026-015870 BP787022025-12-032026-09-082792026
2026-118727 BP787442026-08-182026-09-10232026
2026-007965 BP787312025-11-032026-01-27852026
2026-063070 BP787242026-05-182026-05-1802026
2026-076662 BP787032026-05-172026-06-16302026
2026-129552 BP787312026-05-142026-10-021412026
2026-071210 BP787582026-06-032026-06-0852026
2025-163010 BP787352025-10-062026-01-191052026
2026-034054 BP787312026-01-042026-04-04902026
2026-003682 BP787212026-01-112026-01-1212026
2025-145208 BP787232025-09-282025-11-12452025
2026-104197 BP787512025-05-272026-09-134742026
2022-055330 BP787512021-01-212026-03-0818722026
2026-103752 BP787592026-08-092026-08-0902026
2025-148838 BP787592025-11-182025-11-1912025
2026-092550 BP787462026-07-092026-08-09312026
2026-013194 BP787452025-08-172026-02-211882026
2026-069292 BP787232026-03-012026-06-141052026
2025-116884 BP787052025-06-152026-03-012592026
2026-049785 BP787312026-03-012026-04-22522026
2026-046032 BP787312026-03-222026-04-15242026
2026-109586 BP787032026-04-272026-08-231182026
2026-055904 BP787502026-04-122026-05-06242026
2025-147050 BP787492025-11-132025-11-1302025
2026-053995 BP787562026-03-082026-05-04572026
2026-041659 BP787442026-04-062026-04-0602026
2026-095548 BP787312026-07-222026-07-2752026
2025-146314 BP787232025-10-292025-11-12142025
2026-091615 BP787042026-06-082026-08-03562026

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.