AUSTIN · PERMIT TIMELINES

How long does a kitchen remodel permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

41 calendar days

n = 343 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 343. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-096754 BP787312026-05-212026-07-27672026
2026-004288 BP787452025-11-252026-01-13492026
2026-115093 BP787312026-07-282026-09-01352026
2026-100692 BP787492026-06-252026-08-05412026
2026-047310 BP787312026-04-162026-04-1602026
2026-139251 BP787452026-08-092026-10-25772026
2026-107876 BP787052026-06-242026-08-19562026
2026-063313 BP787452026-05-182026-05-2132026
2026-070827 BP787042026-03-172026-06-08832026
2026-107927 BP787032026-07-212026-08-19292026
2026-033960 BP787492026-01-252026-03-23572026
2026-040913 BP787042026-03-292026-04-14162026
2025-136745 BP787312025-10-212025-11-17272025
2026-081163 BP787562026-04-132026-10-251952026
2026-010392 BP787212025-10-222026-01-28982026
2026-000551 BP787042025-11-042026-01-06632026
2026-026150 BP787582026-01-132026-03-04502026
2026-037209 BP787052026-02-242026-04-06412026
2026-070856 BP787312026-05-252026-07-05412026
2026-020391 BP787232026-02-192026-02-2562026
2026-003554 BP787272026-01-012026-01-14132026
2026-071908 BP787312026-06-042026-06-0732026
2026-022423 BP787272025-10-232026-02-241242026
2025-156152 BP787022025-11-162025-12-09232025
2026-078442 BP787592026-05-202026-06-21322026
2026-061157 BP787312026-05-062026-06-07322026
2026-125005 BP787592026-09-212026-10-13222026
2026-126523 BP787572026-09-102026-09-27172026
2026-120724 BP787572026-08-272026-09-15192026
2026-092227 BP787022026-05-132026-07-21692026
2022-043771 BP787042021-06-082026-05-1818052026
2026-123895 BP787362026-07-282026-09-22562026
2026-031567 BP787572025-11-132026-03-151222026
2026-071950 BP787592026-06-042026-06-0842026
2026-132796 BP787572026-08-302026-10-12432026
2026-102826 BP787032026-07-292026-08-09112026
2026-058673 BP787392026-04-202026-05-11212026
2026-040154 BP787022025-01-212026-04-024362026
2026-073926 BP787452026-06-092026-06-0902026
2026-138258 BP787042026-09-282026-10-25272026
2026-084493 BP787312026-05-262026-06-30352026
2026-023500 BP787032026-01-262026-02-26312026
2026-044476 BP787212026-02-182026-04-12532026
2025-149705 BP787592025-04-032025-12-082492025
2026-098625 BP787232026-03-252026-07-301272026
1999-004108 BP787591999-06-292026-08-3099242026
2026-016120 BP787212026-02-092026-02-22132026
2026-060580 BP787292026-05-112026-08-11922026
2025-129875 BP787312025-10-062026-03-161612026
2026-012711 BP787512025-12-082026-02-17712026

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.