AUSTIN · PERMIT TIMELINES

How long does a roof permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

3 calendar days

n = 162 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 162. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2025-155366 BP787512025-12-072025-12-0812025
2026-091671 BP787492026-06-282026-07-23252026
2026-013129 BP787242026-01-282026-02-08112026
2026-065381 BP787482026-05-212026-05-2102026
2026-118285 BP787222026-09-022026-09-1082026
2026-059978 BP787462026-05-122026-05-1202026
2026-116568 BP787042026-09-032026-09-0302026
2025-153891 BP787232025-12-022025-12-0752025
2026-138659 BP787042026-10-152026-10-25102026
2026-014633 BP787482026-01-192026-02-05172026
2026-083797 BP787452026-06-242026-07-0172026
2026-017469 BP787042026-02-122026-02-1642026
2026-134831 BP787502026-10-122026-10-1532026
2026-068755 BP787442026-05-312026-06-10102026
2026-019287 BP787492026-02-172026-02-2252026
2026-044452 BP787052026-04-122026-04-1312026
2026-038825 BP787032026-03-302026-04-0232026
2026-110283 BP787392026-08-232026-08-2412026
2025-159959 BP787562025-12-112025-12-1762025
2026-014109 BP787032026-02-022026-02-0422026
2026-079540 BP787242026-06-212026-06-2102026
2026-099921 BP787172026-08-022026-08-0312026
2025-132724 BP787262025-10-122025-12-15642025
2025-143931 BP787412025-11-062025-11-0602025
2026-020871 BP787292026-02-192026-02-1902026
2026-055388 BP787022026-05-032026-06-09372026
2026-111746 BP787482026-08-252026-08-2612026
2026-134209 BP787492026-10-112026-10-1102026
2025-140225 BP787502025-10-292025-11-0352025
2026-051761 BP787582026-04-262026-04-2712026
2026-081576 BP787482026-06-242026-06-2952026
2026-010696 BP787442026-01-272026-01-2702026
2026-052308 BP787582026-04-272026-05-0252026
2026-098607 BP787392026-07-292026-08-0242026
2026-033514 BP787502026-03-182026-03-2242026
2026-120248 BP787392026-09-132026-09-1632026
2026-105808 BP787212026-08-032026-08-13102026
2026-102450 BP787452026-08-052026-08-0942026
2026-029862 BP787532026-03-102026-03-1002026
2025-146455 BP787232025-11-032025-11-16132025
2026-023395 BP787532026-02-252026-02-2502026
2026-121712 BP787442026-09-152026-09-1502026
2025-145262 BP787232025-11-112025-11-1102025
2026-060226 BP787512026-05-112026-05-1212026
2026-079395 BP787032026-06-212026-06-2102026
2026-045749 BP787512026-04-122026-08-061162026
2026-136852 BP787172026-10-152026-10-25102026
2026-020365 BP787022026-02-112026-02-26152026
2026-034695 BP787232026-02-222026-03-24302026
2025-147353 BP787292025-11-162025-11-1712025

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.