AUSTIN · PERMIT TIMELINES

How long does a accessory structure permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

78 calendar days

n = 333 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 333. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-004987 BP787042025-09-302026-05-282402026
2026-064418 BP787042026-03-222026-07-151152026
2025-077091 BP787052024-12-022026-04-295132026
2026-036110 BP787472026-02-182026-03-29392026
2026-045929 BP787452026-03-232026-04-26342026
2026-073646 BP787482026-04-082026-06-10632026
2026-067055 BP787452026-04-022026-05-31592026
2026-019957 BP787262025-12-102026-04-051162026
2026-069027 BP787032026-03-312026-08-301522026
2026-108282 BP787512026-06-232026-09-20892026
2026-108687 BP787472026-06-082026-08-25782026
2026-036094 BP787472026-02-182026-03-29392026
2025-089895 BP787322025-04-272026-04-053432026
2026-136459 BP787442026-08-162026-10-27722026
2026-068437 BP787532026-05-282026-06-0142026
2026-028565 BP787452026-02-122026-03-18342026
2026-050843 BP787572026-02-222026-04-29662026
2025-159807 BP787512025-03-142026-02-033262026
2026-002375 BP787572025-10-192026-01-15882026
2025-132789 BP787452025-08-112025-12-011122025
2026-119207 BP787452026-08-132026-09-10282026
2026-135382 BP787562026-08-032026-10-13712026
2026-037090 BP787512025-12-092026-04-201322026
2026-040508 BP787312026-03-102026-04-07282026
2026-004071 BP787032026-01-112026-01-1102026
2026-060003 BP787362026-03-102026-05-18692026
2026-097590 BP787472026-06-082026-07-30522026
2026-128110 BP787482026-04-132026-09-301702026
2026-134344 BP787312026-07-202026-10-13852026
2026-063807 BP787312026-04-292026-05-21222026
2026-011168 BP787312025-11-122026-02-231032026
2014-083095 BP787212014-03-112026-08-3045552026
2026-121231 BP787032026-02-042026-09-172252026
2026-043298 BP787472026-02-162026-04-09522026
2026-032630 BP787442025-11-182026-06-142082026
2026-054078 BP787572026-03-032026-06-241132026
2026-125457 BP787052026-05-032026-09-291492026
2026-042116 BP787472026-02-222026-04-08452026
2026-138129 BP787362026-06-022026-10-251452026
2026-007219 BP787572025-12-082026-02-02562026
2024-065136 BP787512023-08-202026-06-1510302026
2026-017703 BP787572025-12-252026-03-16812026
2026-045236 BP787452025-05-052026-04-163462026
2026-092266 BP787482026-01-152026-07-201862026
2026-104731 BP787032026-05-102026-08-12942026
2026-131188 BP787042026-09-282026-10-19212026
2026-020213 BP787042025-10-202026-02-221252026
2026-054258 BP787232026-02-242026-05-04692026
2026-043575 BP787032026-01-132026-04-09862026
2026-123914 BP787442026-08-192026-10-04462026

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.