AUSTIN · PERMIT TIMELINES

How long does a accessory structure permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

78 calendar days

n = 333 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 333. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2003-013039 BP787512003-02-032026-01-0783742026
2025-162771 BP787022025-07-012026-01-131962026
2026-134787 BP787542026-10-122026-10-1312026
2026-080054 BP787412025-09-142026-06-292882026
2026-000875 BP787522025-10-302026-01-06682026
2025-149972 BP787442025-11-052025-12-07322025
2026-141227 BP787042026-10-072026-10-27202026
2026-080593 BP787392025-11-192026-06-252182026
2026-106476 BP787472026-06-082026-08-18712026
2026-037252 BP787472026-02-222026-04-08452026
2025-058167 BP787032025-04-102026-04-213762026
2026-044969 BP787472026-03-152026-04-14302026
2026-055305 BP787312026-01-282026-05-04962026
2026-001312 BP787042025-09-082026-02-121572026
2025-161124 BP787232025-11-122025-12-21392025
2025-130631 BP787562025-06-252026-08-104112026
2026-040245 BP787472026-03-092026-04-07292026
2026-009972 BP787512025-06-192026-04-213062026
2026-108031 BP787472026-06-082026-08-31842026
2026-045376 BP787262026-02-082026-05-14952026
2026-016650 BP787562026-02-102026-02-1002026
2026-027067 BP787562025-05-062026-04-203492026
2026-031610 BP787462026-01-212026-03-23612026
2025-154488 BP787222025-10-132025-12-14622025
2026-034404 BP787272025-09-232026-03-301882026
2025-161095 BP787032023-06-042026-01-049452026
2026-087361 BP787512026-06-022026-10-191392026
2026-138318 BP787572026-09-152026-10-21362026
2026-109725 BP787222026-04-082026-08-211352026
2026-032455 BP787442025-06-162026-04-193072026
2026-123238 BP786602026-09-172026-09-2032026
2025-149245 BP787022025-09-102025-11-19702025
2026-112434 BP787452026-08-262026-09-0382026
2026-138485 BP787032026-08-242026-10-23602026
2026-053573 BP787312026-03-102026-05-02532026
2026-071008 BP787232026-05-102026-06-04252026
2025-129750 BP787042025-04-282025-11-202062025
2026-108164 BP787532026-04-092026-08-241372026
2025-132074 BP787262025-07-082026-03-022372026
2025-162931 BP787442025-08-242026-01-111402026
2026-110829 BP787582026-06-292026-09-01642026
2026-034147 BP787312026-01-142026-03-22672026
2026-108556 BP787292026-04-122026-08-261362026
2026-126524 BP787572026-09-102026-09-27172026
2026-138991 BP787022026-09-212026-10-25342026
2026-135600 BP787392026-08-302026-10-19502026
2025-141127 BP787032025-08-112025-11-06872025
2026-119306 BP787572026-08-052026-09-14402026
2026-142757 BP787042026-10-012026-10-28272026
2026-033941 BP787482025-12-292026-03-23842026