AUSTIN · PERMIT TIMELINES

How long does a accessory structure permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

78 calendar days

n = 333 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 333. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-028574 BP787042025-11-052026-05-111872026
2026-109724 BP787222026-04-082026-08-211352026
2026-102511 BP787262026-06-092026-08-16682026
2026-046917 BP787462026-02-032026-04-20762026
2026-054039 BP787042026-03-012026-05-11712026
2025-161538 BP787572025-10-212025-12-22622025
2026-012762 BP787302025-11-192026-02-03762026
2026-019020 BP787232026-02-172026-02-2032026
2026-137934 BP787492026-08-272026-10-20542026
2025-145617 BP787032025-04-302025-11-131972025
2026-002877 BP787452025-10-292026-03-051272026
2026-123645 BP787442026-08-122026-09-27462026
2026-103890 BP787502026-07-232026-08-11192026
2026-098222 BP787512026-06-102026-08-03542026
2026-119133 BP787022026-07-132026-10-05842026
2026-004651 BP787522025-08-252026-01-141422026
2026-086123 BP787582026-03-312026-07-07982026
2026-119776 BP787042026-07-142026-09-14622026
2026-042514 BP787462026-01-292026-04-08692026
2026-053674 BP787032025-09-292026-05-202332026
2026-005470 BP787042025-12-142026-07-072052026
2026-046768 BP787482026-04-152026-04-1612026
2026-124062 BP787462026-05-212026-09-201222026
2026-048016 BP787302026-02-112026-04-20682026
2026-109354 BP787562026-05-172026-10-221582026
2026-125094 BP787582026-06-222026-10-181182026
2026-133678 BP787232026-06-282026-10-201142026
2025-132611 BP787592025-06-302026-05-033072026
2026-138177 BP787452026-10-192026-10-2232026
2026-038447 BP787242026-03-302026-04-0232026
2025-138282 BP787592025-05-282026-01-292462026
2026-113746 BP787572026-07-132026-08-30482026
2026-024209 BP787592026-02-262026-03-0242026
2026-029727 BP787452026-03-102026-03-1002026
2025-150216 BP787042025-05-182025-12-082042025
2026-060403 BP787352026-04-022026-05-26542026
2026-075270 BP787312025-07-152026-07-053552026
2026-112562 BP787572026-07-192026-08-31432026
2025-160686 BP787302024-10-162025-12-214312025
2026-022072 BP787232025-11-112026-02-241052026
2026-031711 BP787292025-12-072026-03-171002026
2026-104132 BP787452026-07-082026-08-10332026
2026-062380 BP787392026-03-192026-05-19612026
2026-015643 BP787272025-09-012026-02-231752026
2026-046918 BP787462026-02-032026-05-181042026
2026-108737 BP787032026-06-282026-08-24572026
2022-015006 BP787572021-10-132026-07-0817292026
2026-138577 BP787272026-10-042026-10-26222026
2026-001225 BP787502025-10-162026-01-06822026
2026-112422 BP787032026-06-302026-09-12742026

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.