AUSTIN · PERMIT TIMELINES

How long does a addition permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

60 calendar days

n = 468 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 468. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2025-114120 BP787042025-06-252026-01-081972026
2026-026217 BP787232024-12-022026-04-265102026
2026-129770 BP787502026-09-172026-10-07202026
2025-149064 BP787242025-11-182025-11-1802025
2026-130207 BP787392026-09-232026-10-07142026
2026-050550 BP787592026-03-192026-05-07492026
2026-097168 BP787592026-06-292026-08-18502026
2026-123598 BP787592026-09-102026-09-22122026
2026-083789 BP787502026-06-032026-07-05322026
2025-161354 BP787352025-12-212025-12-2212025
2026-109525 BP787302026-07-162026-08-20352026
2026-140683 BP787222026-04-022026-10-272082026
2026-071188 BP787592026-05-112026-06-09292026
2026-062199 BP787312026-05-052026-05-18132026
2025-157289 BP787232025-09-222025-12-10792025
2025-144253 BP787292025-08-112026-09-013862026
2026-137812 BP787312026-10-042026-10-21172026
2026-071822 BP787042026-04-132026-06-15632026
2026-037692 BP787482026-02-172026-03-30412026
2025-144231 BP787502025-10-152025-11-30462025
2026-043447 BP787042026-02-252026-07-151402026
2026-023201 BP787512026-02-012026-02-28272026
2026-040845 BP787392026-03-112026-04-06262026
2026-010065 BP787172025-08-182026-01-281632026
2025-106713 BP787582025-06-102025-11-121552025
2026-095922 BP787572026-06-112026-07-31502026
2025-155434 BP787582025-11-162026-09-032912026
2026-045235 BP787452025-05-052026-04-163462026
2025-141771 BP787492025-10-212025-11-25352025
2026-104926 BP787312026-05-192026-09-141182026
2025-138644 BP787042025-10-052025-12-01572025
2026-040281 BP787022025-09-242026-04-081962026
2026-007082 BP786532025-11-032026-01-22802026
2026-018804 BP787512026-02-052026-02-17122026
1995-014830 BP787561995-05-072026-08-30114382026
2026-057053 BP787482026-02-262026-06-101042026
2026-011186 BP787232025-10-072026-02-021182026
2025-138722 BP787022025-09-302026-04-171992026
2026-032930 BP787572025-10-202026-03-181492026
2022-071196 BP787442022-01-172025-12-0914222025
2025-158159 BP787232025-11-242025-12-11172025
2026-033404 BP787042026-01-122026-06-141532026
2026-036727 BP787572026-02-262026-03-29312026
2026-034196 BP787532026-01-222026-03-22592026
2026-052342 BP787462026-03-122026-05-18672026
2026-024991 BP787592026-01-082026-03-02532026
2026-013780 BP787312025-10-092026-02-051192026
2026-062834 BP787172026-04-262026-09-171442026
2026-071175 BP787312026-05-202026-06-30412026
2026-001343 BP787042025-07-292026-01-111662026

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.