How long does a addition permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

60 calendar days

n = 468 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 468. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-048771 BP787452026-03-292026-05-06382026
2025-150495 BP787212025-10-052025-12-15712025
2025-093942 BP787032025-01-082026-01-063632026
2026-135649 BP787492026-08-102026-10-22732026
2026-096989 BP787312026-07-082026-07-27192026
2026-038839 BP787442026-03-302026-03-3112026
2026-125631 BP787492026-08-112026-09-24442026
2003-007083 BP787502003-05-062026-09-2885462026
2026-076188 BP787582026-03-082026-06-15992026
2026-038841 BP787442026-03-302026-03-3112026
2026-048535 BP787222025-12-012026-04-261462026
2026-095244 BP787392026-06-222026-07-26342026
2025-159263 BP787392025-04-092026-01-052712026
2026-058399 BP787392026-03-032026-05-28862026
2026-102805 BP787292026-06-212026-08-10502026
2026-017055 BP787042025-10-292026-02-171112026
2026-102481 BP787462026-04-292026-08-111042026
2025-141746 BP787032025-08-062026-01-281752026
2026-042930 BP787022025-12-102026-05-041452026
2026-030110 BP787312025-08-262026-03-192052026
2026-037650 BP787232026-03-192026-03-29102026
2026-039734 BP787442026-04-012026-04-0212026
2026-077926 BP787392026-03-042026-09-171972026
2026-033606 BP787492026-02-052026-04-01552026
2026-005395 BP787512025-08-212026-01-211532026
2026-096090 BP787032026-07-122026-07-28162026
2025-147196 BP787302025-09-142025-12-17942025
2026-058720 BP787312026-05-052026-05-16112026
2026-072634 BP787232026-05-142026-06-10272026
2026-020816 BP787452026-01-112026-02-23432026
2024-037076 BP787042023-06-252026-05-1010502026
2026-132292 BP787352026-10-062026-10-0712026
2026-123826 BP787532026-09-022026-09-21192026
2025-120396 BP787512025-05-182025-11-231892025
2025-159610 BP787442025-12-162026-01-04192026
2025-158772 BP787452025-11-032026-02-10992026
2026-041421 BP787232026-03-052026-04-07332026
2026-048056 BP787172026-03-042026-04-19462026
2025-158621 BP787042025-10-132025-12-14622025
2026-042373 BP787242026-03-022026-04-13422026
2026-000299 BP787592025-10-262026-01-26922026
2026-091360 BP787462026-06-082026-07-15372026
2026-021919 BP787212025-07-282026-03-162312026
2026-075056 BP787232026-03-242026-06-11792026
2026-011758 BP787502025-11-242026-02-02702026
2025-154997 BP787042025-09-212025-12-28982025
2026-037772 BP787022025-06-032026-04-073082026
2026-093114 BP787302026-06-302026-07-20202026
2026-087473 BP787592026-01-292026-07-161682026
2026-092975 BP787452026-06-022026-07-26542026

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.