AUSTIN · PERMIT TIMELINES

How long does a addition permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

60 calendar days

n = 468 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 468. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-086558 BP787592026-06-162026-07-12262026
2026-096025 BP787022026-06-152026-08-05512026
2026-020474 BP787572025-12-292026-02-22552026
2026-117441 BP787312026-08-252026-09-13192026
2026-114169 BP787352026-06-292026-09-22852026
2026-115073 BP787452026-06-032026-09-08972026
2026-001625 BP787312025-12-092026-01-17392026
2025-103034 BP787052025-05-042026-02-182902026
2026-092155 BP787572026-05-182026-08-17912026
2025-129254 BP787592025-08-182025-12-281322025
2026-085118 BP787232026-03-092026-07-061192026
2026-080793 BP787532026-05-272026-08-06712026
2026-065361 BP787242026-05-212026-05-2542026
2026-003218 BP787312025-11-162026-01-12572026
2026-083118 BP787582026-04-302026-07-05662026
2026-040021 BP786172026-04-012026-04-12112026
2026-086124 BP787582026-03-312026-07-07982026
2026-094572 BP787172026-04-292026-08-231162026
2026-133471 BP787462026-04-202026-10-271902026
2026-030820 BP787592026-01-282026-03-23542026
2024-024586 BP787462023-09-102026-10-1211282026
2026-092013 BP787312026-05-272026-07-19532026
2026-082080 BP787392026-05-262026-06-30352026
2026-126538 BP787052026-09-152026-09-28132026
2026-000593 BP787262025-10-192026-01-08812026
2026-012065 BP787592025-12-042026-02-17752026
2025-059839 BP787042025-01-282025-12-163222025
2026-048392 BP787222026-03-052026-04-20462026
2026-083727 BP787392026-06-032026-06-30272026
2026-093328 BP787452026-02-172026-08-261902026
2026-126597 BP787032026-08-102026-09-28492026
2026-066158 BP787232026-05-042026-05-27232026
2026-114264 BP787592025-12-102026-09-062702026
2026-087089 BP787032026-04-212026-07-28982026
2026-039707 BP787442026-04-012026-04-0212026
2026-074916 BP787172026-05-182026-08-19932026
2026-026999 BP787272025-09-142026-03-051722026
2026-118708 BP787312026-08-182026-09-10232026
2026-010583 BP787222025-09-102026-01-281402026
2026-024474 BP787502026-02-102026-03-02202026
2026-003564 BP787022025-11-162026-01-25702026
2026-120309 BP787522026-07-272026-09-14492026
2026-140035 BP787302026-10-052026-10-27222026
2025-162784 BP787232025-12-012026-01-07372026
2025-153459 BP787242025-12-022025-12-0752025
2025-141780 BP787572025-01-262025-11-052832025
2026-094616 BP787462026-06-282026-07-22242026
2025-153018 BP787312025-11-112026-01-04542026
2026-040137 BP787572025-12-022026-04-081272026
2022-131146 BP787462022-05-192026-07-1915222026