AUSTIN · PERMIT TIMELINES

How long does a addition permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

60 calendar days

n = 468 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 468. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2025-150318 BP787592024-12-082025-11-233502025
2026-110250 BP787312026-08-112026-08-26152026
2026-090318 BP787572026-05-202026-07-16572026
2026-133227 BP787352026-06-092026-10-081212026
2026-038462 BP787442026-03-302026-03-3002026
2026-143774 BP787532026-10-292026-10-2902026
2026-000310 BP787242026-01-012026-01-0102026
2026-032901 BP787492026-01-192026-03-18582026
2026-061499 BP787222026-04-222026-05-19272026
2026-051644 BP787312026-04-092026-05-16372026
2025-147214 BP787592025-09-212025-12-28982025
2026-071191 BP787442026-05-132026-07-19672026
2026-048851 BP787032025-12-302026-05-061272026
2026-137791 BP786172026-08-302026-10-28592026
2026-048565 BP787442026-01-132026-04-291062026
2026-089709 BP787052026-06-172026-07-14272026
2025-156193 BP787212025-12-082025-12-0802025
2026-092993 BP787312026-05-072026-07-20742026
2025-160711 BP787452025-11-122025-12-21392025
2025-134548 BP787032025-06-042025-11-241732025
2026-100655 BP787312026-06-212026-09-03742026
2026-026198 BP787272026-02-102026-03-04222026
2026-038570 BP787442026-03-302026-03-3002026
2025-147945 BP787572025-10-132025-11-18362025
2026-030378 BP787592025-11-172026-03-151182026
2026-012595 BP787462025-11-052026-02-10972026
2026-004454 BP787032025-08-212026-01-141462026
2026-047730 BP787462026-02-252026-04-21552026
2003-011539 BP787592003-09-252025-11-0480762025
2026-050688 BP787392025-10-022026-08-063082026
2026-082860 BP787452025-02-252026-07-074972026
2026-013497 BP787492025-12-072026-02-05602026
2026-083344 BP787442026-06-032026-07-05322026
2026-038803 BP787022025-10-052026-04-061832026
2026-039558 BP787442026-03-312026-04-0222026
2026-109198 BP787492026-07-192026-08-27392026
2025-154564 BP787472025-08-042025-12-071252025
2026-064712 BP787572026-04-302026-05-27272026
2026-006308 BP787312025-08-172026-02-191862026
2025-163470 BP787492025-10-062026-01-05912026
2025-125199 BP787042025-08-062025-11-06922025
2026-040003 BP786172026-04-012026-04-12112026
2026-133362 BP787452026-04-022026-10-141952026
2026-063579 BP787262026-05-112026-05-2092026
2026-098137 BP787452026-07-142026-08-06232026
2026-024000 BP787032026-02-172026-02-2692026
2026-029160 BP787272026-01-212026-03-12502026
2026-136743 BP787502026-09-162026-10-19332026
2026-113046 BP787312026-07-192026-09-07502026
2026-105855 BP787592026-07-132026-09-08572026

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.