AUSTIN · PERMIT TIMELINES
How long does a addition permit take in Austin?
Median application-to-issuance time
60 calendar days
n = 468 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.
Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.
Explore the ZIP-level record
Records used in this calculation
Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 468. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.
| Permit | ZIP | Applied | Issued | Calendar days | Source year |
|---|---|---|---|---|---|
| 2025-150318 BP | 78759 | 2024-12-08 | 2025-11-23 | 350 | 2025 |
| 2026-110250 BP | 78731 | 2026-08-11 | 2026-08-26 | 15 | 2026 |
| 2026-090318 BP | 78757 | 2026-05-20 | 2026-07-16 | 57 | 2026 |
| 2026-133227 BP | 78735 | 2026-06-09 | 2026-10-08 | 121 | 2026 |
| 2026-038462 BP | 78744 | 2026-03-30 | 2026-03-30 | 0 | 2026 |
| 2026-143774 BP | 78753 | 2026-10-29 | 2026-10-29 | 0 | 2026 |
| 2026-000310 BP | 78724 | 2026-01-01 | 2026-01-01 | 0 | 2026 |
| 2026-032901 BP | 78749 | 2026-01-19 | 2026-03-18 | 58 | 2026 |
| 2026-061499 BP | 78722 | 2026-04-22 | 2026-05-19 | 27 | 2026 |
| 2026-051644 BP | 78731 | 2026-04-09 | 2026-05-16 | 37 | 2026 |
| 2025-147214 BP | 78759 | 2025-09-21 | 2025-12-28 | 98 | 2025 |
| 2026-071191 BP | 78744 | 2026-05-13 | 2026-07-19 | 67 | 2026 |
| 2026-048851 BP | 78703 | 2025-12-30 | 2026-05-06 | 127 | 2026 |
| 2026-137791 BP | 78617 | 2026-08-30 | 2026-10-28 | 59 | 2026 |
| 2026-048565 BP | 78744 | 2026-01-13 | 2026-04-29 | 106 | 2026 |
| 2026-089709 BP | 78705 | 2026-06-17 | 2026-07-14 | 27 | 2026 |
| 2025-156193 BP | 78721 | 2025-12-08 | 2025-12-08 | 0 | 2025 |
| 2026-092993 BP | 78731 | 2026-05-07 | 2026-07-20 | 74 | 2026 |
| 2025-160711 BP | 78745 | 2025-11-12 | 2025-12-21 | 39 | 2025 |
| 2025-134548 BP | 78703 | 2025-06-04 | 2025-11-24 | 173 | 2025 |
| 2026-100655 BP | 78731 | 2026-06-21 | 2026-09-03 | 74 | 2026 |
| 2026-026198 BP | 78727 | 2026-02-10 | 2026-03-04 | 22 | 2026 |
| 2026-038570 BP | 78744 | 2026-03-30 | 2026-03-30 | 0 | 2026 |
| 2025-147945 BP | 78757 | 2025-10-13 | 2025-11-18 | 36 | 2025 |
| 2026-030378 BP | 78759 | 2025-11-17 | 2026-03-15 | 118 | 2026 |
| 2026-012595 BP | 78746 | 2025-11-05 | 2026-02-10 | 97 | 2026 |
| 2026-004454 BP | 78703 | 2025-08-21 | 2026-01-14 | 146 | 2026 |
| 2026-047730 BP | 78746 | 2026-02-25 | 2026-04-21 | 55 | 2026 |
| 2003-011539 BP | 78759 | 2003-09-25 | 2025-11-04 | 8076 | 2025 |
| 2026-050688 BP | 78739 | 2025-10-02 | 2026-08-06 | 308 | 2026 |
| 2026-082860 BP | 78745 | 2025-02-25 | 2026-07-07 | 497 | 2026 |
| 2026-013497 BP | 78749 | 2025-12-07 | 2026-02-05 | 60 | 2026 |
| 2026-083344 BP | 78744 | 2026-06-03 | 2026-07-05 | 32 | 2026 |
| 2026-038803 BP | 78702 | 2025-10-05 | 2026-04-06 | 183 | 2026 |
| 2026-039558 BP | 78744 | 2026-03-31 | 2026-04-02 | 2 | 2026 |
| 2026-109198 BP | 78749 | 2026-07-19 | 2026-08-27 | 39 | 2026 |
| 2025-154564 BP | 78747 | 2025-08-04 | 2025-12-07 | 125 | 2025 |
| 2026-064712 BP | 78757 | 2026-04-30 | 2026-05-27 | 27 | 2026 |
| 2026-006308 BP | 78731 | 2025-08-17 | 2026-02-19 | 186 | 2026 |
| 2025-163470 BP | 78749 | 2025-10-06 | 2026-01-05 | 91 | 2026 |
| 2025-125199 BP | 78704 | 2025-08-06 | 2025-11-06 | 92 | 2025 |
| 2026-040003 BP | 78617 | 2026-04-01 | 2026-04-12 | 11 | 2026 |
| 2026-133362 BP | 78745 | 2026-04-02 | 2026-10-14 | 195 | 2026 |
| 2026-063579 BP | 78726 | 2026-05-11 | 2026-05-20 | 9 | 2026 |
| 2026-098137 BP | 78745 | 2026-07-14 | 2026-08-06 | 23 | 2026 |
| 2026-024000 BP | 78703 | 2026-02-17 | 2026-02-26 | 9 | 2026 |
| 2026-029160 BP | 78727 | 2026-01-21 | 2026-03-12 | 50 | 2026 |
| 2026-136743 BP | 78750 | 2026-09-16 | 2026-10-19 | 33 | 2026 |
| 2026-113046 BP | 78731 | 2026-07-19 | 2026-09-07 | 50 | 2026 |
| 2026-105855 BP | 78759 | 2026-07-13 | 2026-09-08 | 57 | 2026 |
PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.