AUSTIN · PERMIT TIMELINES

How long does a bathroom remodel permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

53 calendar days

n = 425 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 425. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-044986 BP787022026-01-142026-05-161222026
2026-032689 BP787022026-03-172026-03-2252026
2026-052206 BP787492026-01-212026-04-29982026
2026-027730 BP787172026-01-222026-03-08452026
2026-128228 BP787032026-08-172026-10-05492026
2026-055087 BP787212026-05-032026-05-0302026
2026-068015 BP787462025-12-112026-05-311712026
2026-134630 BP787462025-06-152026-10-154872026
2026-087284 BP787502026-05-052026-07-08642026
2026-067326 BP787442026-05-272026-06-0372026
2026-098948 BP787032026-07-282026-08-0252026
2026-013462 BP787482026-01-112026-02-11312026
2025-140755 BP787052025-08-112025-11-251062025
2026-098219 BP787512026-06-102026-08-02532026
2026-129794 BP787452026-10-012026-10-0102026
2025-148161 BP787532025-11-112025-11-24132025
2025-146869 BP787232025-09-032025-11-23812025
2022-093202 BP787462022-05-082025-12-1013122025
2026-034204 BP787312026-01-192026-03-22622026
2026-030260 BP787572026-03-112026-09-101832026
2026-111044 BP787572026-08-112026-08-24132026
2026-050782 BP787442026-04-232026-04-2742026
2026-091140 BP787442026-07-142026-07-1402026
2026-103113 BP787412026-01-142026-08-312292026
2026-012697 BP787592026-02-022026-02-0202026
2026-037325 BP787272026-03-182026-03-29112026
2026-017693 BP787532025-11-202026-03-261262026
2026-064194 BP787572026-02-182026-05-26972026
2026-074600 BP787502026-06-102026-06-1662026
2026-074381 BP787592026-05-172026-06-10242026
2026-023995 BP787572025-12-072026-03-16992026
2026-032782 BP787532026-03-172026-03-1702026
2026-041140 BP787502026-03-162026-04-06212026
2026-022420 BP787512026-01-262026-03-01342026
2026-033476 BP787592026-02-192026-03-18272026
2026-075445 BP787312026-06-112026-06-1102026
2026-036283 BP787492026-03-252026-03-2612026
2025-089559 BP787042024-10-092025-12-024192025
2026-136808 BP787032026-05-182026-10-251602026
2025-160208 BP787032025-08-072026-01-051512026
2025-145932 BP787442025-11-122025-11-1202025
2026-091738 BP787032026-03-242026-07-211192026
2026-063250 BP787482026-05-032026-05-21182026
2025-159208 BP787022025-11-202026-01-05462026
2025-155545 BP787032024-11-072026-05-285672026
2026-040016 BP787592026-01-082026-04-03852026
2026-097334 BP787582026-07-272026-07-2812026
2025-145928 BP787022025-10-142026-01-20982026
2025-151496 BP787302025-05-272025-12-121992025
2025-152836 BP787572025-09-142026-02-271662026

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.