How long does a bathroom remodel permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

53 calendar days

n = 425 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 425. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2025-147376 BP787452025-11-162025-11-1602025
2026-071630 BP787212026-05-282026-06-0472026
2026-135052 BP787022026-10-062026-10-1592026
2026-111194 BP787442026-08-242026-08-2402026
2026-028557 BP787232026-02-122026-04-06532026
2026-043593 BP787462026-03-162026-04-14292026
2026-013210 BP787032025-08-112026-02-081812026
2026-125788 BP787532026-09-072026-09-24172026
2026-109753 BP787312026-08-202026-08-2002026
2025-052370 BP787452024-12-102026-02-234402026
2026-035701 BP787312026-02-042026-03-29532026
2025-161788 BP787352025-10-292025-12-29612025
2026-089000 BP787042026-07-092026-07-21122026
2026-100985 BP787502026-06-252026-08-04402026
2026-037083 BP787032026-03-192026-04-06182026
2026-095822 BP787572026-07-232026-07-2302026
2026-056305 BP787052026-02-222026-06-01992026
2026-105102 BP787232026-07-192026-08-12242026
2026-117848 BP787592026-06-162026-09-09852026
2026-116231 BP787312026-08-102026-09-08292026
2026-092370 BP787232026-05-032026-07-21792026
2026-079206 BP787212026-06-212026-06-2102026
2025-138609 BP787302025-06-162025-12-081752025
2026-050632 BP787492026-04-222026-04-2642026
2026-115384 BP787572026-07-222026-09-02422026
2026-004986 BP787042025-09-302026-05-282402026
2026-011609 BP787442026-01-292026-02-0462026
2026-142580 BP787032026-09-092026-10-27482026
2026-068840 BP787232026-05-312026-05-3102026
2025-158427 BP787312025-12-022025-12-14122025
2026-116230 BP787392026-07-012026-09-07682026
2026-133063 BP787232026-08-062026-10-27822026
2026-046614 BP787572026-01-042026-06-021492026
2026-092737 BP787512026-07-162026-08-02172026
2026-046484 BP787452025-08-102026-05-132762026
2026-104724 BP787572026-07-072026-08-12362026
2026-003802 BP787492025-11-172026-01-24682026
2025-143678 BP787492025-10-072025-11-09332025
2025-001227 BP787322024-09-182026-04-225812026
2026-018771 BP787572025-12-102026-05-261672026
2026-083345 BP787042026-06-282026-07-08102026
2026-073206 BP787312026-05-072026-06-24482026
2026-112697 BP787452026-07-222026-08-30392026
2026-059431 BP787592026-03-292026-06-01642026
2026-117352 BP787572026-08-202026-09-27382026
2026-038346 BP787052026-01-082026-03-31822026
2026-009584 BP787042025-12-282026-01-26292026
2026-096082 BP787462026-07-082026-07-23152026
2025-155544 BP787032024-11-072026-05-285672026
2025-157085 BP787032025-11-092025-12-25462025