How long does a bathroom remodel permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

53 calendar days

n = 425 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 425. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-037091 BP787512025-12-092026-04-201322026
2026-037230 BP787592026-03-032026-03-30272026
2026-123735 BP787572025-11-122026-10-273492026
2026-011703 BP787052026-01-212026-03-10482026
2026-044377 BP787232026-03-312026-04-15152026
2026-055428 BP787212026-04-302026-05-0332026
2026-067576 BP787032026-04-182026-08-241282026
2026-081587 BP787532026-06-242026-06-2952026
2026-054707 BP787042026-04-262026-06-24592026
2026-096812 BP787452026-06-302026-07-26262026
2026-050122 BP787512026-04-202026-04-2332026
2026-098946 BP787502026-07-292026-08-0352026
2026-136183 BP787442026-08-042026-10-26832026
2026-131236 BP787572026-09-152026-10-07222026
2025-138678 BP787232025-10-262025-11-05102025
2026-082958 BP787042026-04-052026-06-29852026
2026-135962 BP787532026-10-132026-10-1852026
2026-067489 BP787412026-05-062026-06-08332026
2026-138138 BP787212026-07-092026-10-291122026
2026-117286 BP787502026-08-232026-09-08162026
2024-037077 BP787042023-06-252026-05-1010502026
2026-109864 BP787512026-07-062026-10-181042026
2026-084960 BP787042026-07-012026-07-0982026
2026-008654 BP787452025-07-242026-03-102292026
2026-128363 BP787482026-08-112026-10-21712026
2026-067838 BP787452026-05-272026-05-2702026
2026-125967 BP787022025-11-132026-10-193402026
2026-123122 BP787042026-07-132026-09-30792026
2026-140716 BP787312026-08-122026-10-27762026
2026-106423 BP787022026-06-232026-09-16852026
2026-082339 BP787212026-06-252026-06-2832026
2025-147852 BP787522025-10-152025-11-21372025
2026-074781 BP786172026-06-102026-06-21112026
2025-145638 BP787532025-11-112025-11-1102025
2026-027994 BP787392026-03-082026-03-25172026
2026-007421 BP787022025-08-142026-02-111812026
2026-065515 BP787492026-05-212026-05-2432026
2026-068009 BP787272026-04-292026-05-28292026
2026-092067 BP787572026-05-052026-07-19752026
2025-115174 BP787322025-09-022025-12-04932025
2025-159384 BP787482025-10-082025-12-17702025
2026-040113 BP787482026-02-022026-04-06632026
2025-038970 BP786172024-10-012026-07-086452026
2026-005772 BP787312025-12-212026-04-141142026
2026-102137 BP787172026-06-042026-08-12692026
2025-148537 BP787472025-08-262025-12-02982025
2026-047081 BP787022026-04-152026-04-1502026
2026-034164 BP787452026-01-202026-05-101102026
2026-048185 BP787312026-04-082026-04-27192026
2026-024554 BP787502025-10-082026-03-031462026

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.