AUSTIN · PERMIT TIMELINES

How long does a bathroom remodel permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

53 calendar days

n = 425 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 425. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-047281 BP787512026-01-192026-07-261882026
2026-019025 BP787262026-02-172026-02-1812026
2026-004477 BP787272025-12-142026-01-16332026
2026-030886 BP787312026-02-162026-03-16282026
2026-000107 BP787502026-01-012026-01-0102026
2026-132809 BP787242026-10-072026-10-1142026
2000-006843 BP787572000-08-102026-08-2095062026
2026-028137 BP787442025-09-252026-03-091652026
2026-091290 BP787262026-04-302026-07-16772026
2026-116343 BP787572026-09-022026-09-0642026
2026-038020 BP787032025-12-212026-06-071682026
2026-090869 BP787562026-06-032026-07-29562026
2026-082573 BP787232026-04-292026-07-01632026
2025-102093 BP787462025-07-012026-06-103442026
2025-151392 BP787452025-08-252025-12-031002025
2026-015379 BP787492025-12-172026-02-20652026
2025-160007 BP787462025-07-092025-12-221662025
2026-053471 BP787392026-04-282026-04-3022026
2026-132898 BP787572026-09-022026-10-21492026
2026-000200 BP787272026-01-012026-01-0102026
2025-144406 BP787172025-10-122025-11-16352025
2026-004279 BP787512025-11-232026-09-243052026
2026-087799 BP787472026-07-072026-07-0702026
2026-017702 BP787572025-12-252026-03-16812026
2026-109595 BP787312026-06-242026-09-09772026
2025-099656 BP787022023-10-022025-12-108002025
2026-024079 BP787562026-02-102026-03-02202026
2025-115973 BP787042025-08-102025-11-201022025
2026-132829 BP787592026-07-202026-10-12842026
2026-047280 BP787512026-01-192026-06-251572026
2025-139847 BP787032025-10-132025-11-12302025
2026-002985 BP787452026-01-082026-01-0802026
2026-086957 BP787312026-05-192026-07-07492026
2026-050803 BP787482026-04-232026-04-2742026
2026-048439 BP787032026-01-142026-04-21972026
2026-109741 BP787492026-08-202026-08-2222026
2026-047516 BP787032026-02-082026-04-19702026
2026-009490 BP787052025-11-132026-02-02812026
2026-000939 BP787042025-08-192026-03-292222026
2026-084791 BP787032026-04-222026-07-05742026
2025-147794 BP787032025-10-012025-11-18482025
2025-142773 BP787462025-09-102026-03-241952026
2025-148031 BP787212025-11-172025-11-1702025
2026-083996 BP787482026-06-292026-07-14152026
2026-078596 BP787222026-03-032026-09-161972026
2026-067183 BP787032026-04-152026-05-27422026
2026-104831 BP787412026-07-282026-08-11142026
2026-013991 BP787572025-09-162026-02-241612026
2026-018854 BP787582025-12-292026-06-011542026
2026-095175 BP787572026-06-082026-07-26482026

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.