AUSTIN · PERMIT TIMELINES

How long does a interior alteration permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

3 calendar days

n = 2424 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 2424. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-034518 BP787592026-03-222026-04-02112026
2026-106935 BP787452026-08-162026-09-14292026
2026-024883 BP787452026-03-012026-03-0102026
2025-132079 BP787032025-10-092025-11-18402025
2026-020472 BP787542026-02-192026-02-2232026
2026-067065 BP787352026-05-262026-05-2822026
2026-002437 BP787442026-01-072026-01-0702026
2026-131376 BP787542026-10-052026-10-0502026
2026-073694 BP787512026-06-082026-06-0912026
2025-148155 BP787592025-11-172025-11-1702025
2026-086059 BP787452026-07-052026-07-0942026
2026-053371 BP786172026-04-282026-04-2912026
2026-107702 BP787492026-08-172026-08-1702026
2026-074632 BP787492026-06-102026-07-15352026
2025-150846 BP787582025-11-232025-11-2302025
2026-074862 BP787482026-06-102026-06-1112026
2026-001801 BP787262026-01-062026-01-0602026
2026-083101 BP787242026-06-282026-06-2802026
2026-006913 BP787232026-01-192026-01-2122026
2026-017172 BP787482026-02-112026-02-1872026
2026-131197 BP787512026-10-012026-10-12112026
2026-044419 BP787392026-04-122026-04-1202026
2026-011207 BP787452026-01-282026-01-2802026
2026-025928 BP787232026-03-032026-03-0302026
2022-059468 BP787452022-04-262026-02-0213782026
2026-003631 BP787482026-01-112026-01-1212026
2025-150967 BP787482025-11-232025-12-29362025
2025-157278 BP787222025-12-102025-12-1112025
2026-059160 BP787312026-05-112026-05-27162026
2025-154743 BP787532025-11-302025-12-0992025
2025-149112 BP786172025-11-182025-11-30122025
2026-144480 BP787572026-11-012026-11-0102026
2026-109650 BP787272026-08-202026-08-2002026
2026-010573 BP787482026-01-272026-01-2702026
2026-060427 BP787592026-05-122026-08-231032026
2025-145291 BP787492025-11-112025-11-1872025
2026-109612 BP787452026-08-202026-08-2332026
2026-126888 BP787482026-09-242026-09-2842026
2026-081092 BP787452026-06-232026-06-2852026
2025-152459 BP787042025-11-302025-11-3002025
2026-067388 BP787272026-05-272026-05-2702026
2026-016730 BP787502026-02-102026-02-1002026
2026-074541 BP787562026-06-102026-06-1002026
2026-050760 BP787592026-04-232026-04-2742026
2025-163285 BP787492025-12-292026-01-27292026
2026-005751 BP787532026-01-142026-01-1402026
2026-083063 BP787232026-06-282026-07-22242026
2026-081876 BP787262026-06-222026-08-04432026
2026-098242 BP787032026-07-282026-07-2802026
2026-127868 BP787452026-09-282026-10-21232026

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.