AUSTIN · PERMIT TIMELINES

How long does a kitchen remodel permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

41 calendar days

n = 343 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 343. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-130502 BP787492026-09-032026-10-06332026
2026-139397 BP787592026-06-222026-10-211212026
2026-027562 BP787572026-03-052026-03-1052026
2026-120408 BP787312026-08-122026-09-14332026
2026-123628 BP787452026-08-022026-09-23522026
2025-145629 BP787232025-11-112025-11-1102025
2026-039644 BP787352026-02-162026-04-02452026
2026-140238 BP787312026-08-192026-10-29712026
2026-073444 BP787462026-04-162026-06-23682026
2026-105158 BP787032026-06-302026-08-12432026
2026-048572 BP787582026-03-302026-04-20212026
2026-051689 BP787032026-03-192026-04-28402026
2026-114878 BP787512026-05-132026-09-031132026
2026-129389 BP787232026-08-062026-10-01562026
2026-081919 BP787592026-06-072026-06-28212026
2026-069443 BP787572025-12-112026-06-071782026
2026-098098 BP787032025-01-222026-08-095642026
2025-075597 BP787452025-04-132026-02-032962026
2025-082993 BP787032025-04-272026-04-133512026
2026-060108 BP787452026-05-122026-05-1202026
2026-092303 BP787572026-06-022026-10-221422026
2026-104758 BP787492026-06-242026-08-13502026
2026-015853 BP787312026-01-282026-02-11142026
2026-013909 BP787032026-01-072026-02-11352026
2026-078481 BP787452026-05-252026-06-22282026
2026-091124 BP787482026-06-222026-07-14222026
2025-161663 BP787452025-12-222025-12-2202025
2026-034176 BP787492026-01-252026-03-22562026
2026-118699 BP787022026-08-252026-09-14202026
2026-017781 BP787492025-10-212026-02-181202026
2026-121593 BP787452026-07-142026-09-29772026
2026-044371 BP787562026-03-112026-05-03532026
2026-017211 BP787572026-01-202026-02-18292026
2025-157060 BP787312025-10-122026-01-19992026
2026-004606 BP787502025-12-292026-01-13152026
2025-138118 BP787592025-09-242025-11-06432025
2026-056180 BP787502026-04-292026-05-18192026
2025-078300 BP787032025-05-182025-12-102062025
2026-118198 BP787492026-07-262026-09-19552026
2026-121005 BP787222026-08-122026-09-15342026
2026-069501 BP787462026-04-262026-06-01362026
2025-022131 BP787032024-12-252025-12-023422025
2026-108322 BP787592026-05-182026-08-301042026
2025-158123 BP787312025-12-032025-12-14112025
2026-055168 BP787482026-05-032026-07-29872026
2026-081299 BP787482026-06-232026-06-2962026
2026-048967 BP787572026-03-262026-04-27322026
2026-029108 BP787272026-02-182026-03-11212026
2026-087804 BP787592026-06-092026-07-08292026
2025-151591 BP787462025-09-072025-12-02862025

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.