AUSTIN · PERMIT TIMELINES

How long does a kitchen remodel permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

41 calendar days

n = 343 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 343. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-130170 BP787312026-08-192026-10-18602026
2026-103492 BP787052026-08-092026-08-0902026
2026-072642 BP787352026-05-312026-06-11112026
2026-134282 BP787302026-09-302026-10-12122026
2026-142594 BP787032026-08-032026-10-28862026
2026-137129 BP787042026-08-232026-10-25632026
2026-067512 BP787572026-03-152026-06-11882026
2026-099373 BP787572026-05-052026-09-071252026
2026-016891 BP787582026-02-042026-02-1172026
2025-150838 BP787312025-11-022026-02-231132026
2026-126386 BP787312026-09-232026-09-2412026
2026-043259 BP787452026-03-172026-04-09232026
2026-013980 BP787462025-11-022026-02-05952026
2026-101036 BP787392026-07-122026-08-12312026
2026-141496 BP787412026-10-202026-10-2772026
2026-060407 BP787562026-02-122026-05-16932026
2025-163535 BP787492025-10-212026-04-051662026
2026-033273 BP787312026-03-152026-03-1942026
2026-109761 BP787232026-08-052026-08-23182026
2026-004080 BP787502025-11-242026-01-12492026
2025-163095 BP787502025-11-182026-01-04472026
2025-029002 BP787032025-01-232026-01-213632026
2026-036605 BP787032026-01-012026-03-26842026
2026-105664 BP787312026-05-032026-08-121012026
2026-124152 BP787562026-07-162026-09-28742026
2026-043520 BP787222026-03-042026-08-091582026
2025-151502 BP787512025-11-242025-11-2512025
2025-143828 BP787312025-11-062025-11-0602025
2025-150248 BP787042025-06-122025-11-241652025
2026-109245 BP787032026-07-212026-08-23332026
2026-057222 BP787052026-04-082026-05-11332026
2026-034423 BP787472026-02-232026-03-23282026
2026-112430 BP787232026-08-202026-08-30102026
2026-020216 BP787452026-02-112026-02-1872026
2026-062846 BP787592026-05-072026-05-25182026
2026-093648 BP787022026-05-032026-08-09982026
2023-144342 BP787042022-11-222025-12-2111252025
2025-149770 BP787042025-11-192025-11-2012025
2026-035244 BP787452026-03-232026-03-3072026
2026-020831 BP787572026-01-082026-03-01522026
2026-091173 BP787222026-07-142026-07-1512026
2025-148573 BP787452025-11-182025-11-1802025
2026-000163 BP787042025-10-162026-01-04802026
2026-116762 BP787312026-08-132026-10-27752026
2026-068379 BP787212026-05-062026-06-02272026
2026-106167 BP787312025-11-042026-08-162852026
2026-015224 BP787572026-01-072026-02-09332026
2026-060538 BP787452026-04-092026-05-17382026
2026-006230 BP787312026-01-012026-02-07372026
2026-053419 BP787212026-02-232026-04-30662026

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.