AUSTIN · PERMIT TIMELINES

How long does a interior alteration permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

3 calendar days

n = 2424 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 2424. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-077921 BP787482026-06-162026-06-2152026
2026-139276 BP787492026-10-212026-10-2102026
2025-152396 BP787522025-11-302025-11-3002025
2026-071370 BP787452026-06-032026-06-0412026
2026-008961 BP787022026-01-222026-01-2532026
2026-030222 BP787412026-03-112026-03-1542026
2025-152047 BP786602025-11-252025-11-3052025
2026-107673 BP787442026-08-172026-08-1812026
2026-046216 BP786172026-04-072026-04-1472026
2026-035783 BP787452026-03-242026-03-2512026
2026-096231 BP787412026-07-162026-07-2372026
2025-162080 BP787542025-12-252026-01-0172026
2026-135249 BP787472026-10-132026-10-1852026
2026-023530 BP787542026-02-252026-03-0362026
2026-137995 BP787562026-10-192026-10-1902026
2026-100379 BP787492026-08-022026-08-0202026
2026-002845 BP787592026-01-072026-01-28212026
2026-040070 BP787482026-04-012026-04-0102026
2026-017743 BP787542026-02-122026-03-03192026
2026-089478 BP787222026-07-122026-07-1532026
2025-123989 BP787312025-09-282026-03-161692026
2026-041306 BP787542026-04-052026-04-1492026
2026-046361 BP787232026-04-142026-04-1402026
2026-056782 BP787482026-05-052026-05-0612026
2026-096549 BP787412026-07-192026-07-2782026
2026-077524 BP787462026-06-112026-06-1652026
2026-139665 BP787572026-10-192026-10-2562026
2025-146878 BP787592025-11-132025-12-17342025
2026-107295 BP787452026-08-162026-08-1932026
2026-044483 BP787472026-04-122026-04-1202026
2026-092601 BP787452026-07-162026-07-1932026
2026-067566 BP787512026-05-272026-05-2702026
2026-133111 BP787482026-10-082026-10-0802026
2025-145750 BP787462025-11-032025-11-1182025
2026-001279 BP787452026-01-052026-01-0502026
2026-045798 BP787492026-04-132026-04-1632026
2026-116730 BP787462026-09-032026-10-15422026
2026-012513 BP787392026-02-012026-02-0212026
2025-140894 BP786172025-10-302025-11-11122025
2026-036829 BP787592026-03-252026-03-2612026
2026-097348 BP787032026-07-272026-09-20552026
2025-158934 BP786522025-12-152025-12-2162025
2026-040515 BP787022026-03-262026-04-08132026
2026-047171 BP787042026-04-152026-05-13282026
2026-039665 BP787462026-03-302026-04-0892026
2026-031003 BP787532026-03-122026-03-1642026
2026-089237 BP787542026-07-092026-07-0902026
2026-040354 BP787532026-04-022026-04-0202026
2026-053841 BP786172026-04-292026-05-0452026
2025-141880 BP787222025-11-022025-11-0312025

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.