AUSTIN · PERMIT TIMELINES

How long does a interior alteration permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

3 calendar days

n = 2424 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 2424. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-138627 BP787472026-10-202026-10-2222026
2026-064764 BP787022026-05-202026-05-2662026
2026-083213 BP787232026-06-282026-07-19212026
2026-131459 BP787022026-09-022026-10-06342026
2026-093059 BP787312026-07-192026-08-02142026
2026-035522 BP787472026-03-232026-03-2522026
2026-082369 BP787512026-06-252026-06-2832026
2026-055057 BP787482026-05-032026-05-0742026
2026-109918 BP787412026-08-182026-08-2352026
2026-099535 BP787452026-07-302026-07-3002026
2026-043093 BP787482026-04-082026-04-0802026
2026-097346 BP787392026-07-272026-08-20242026
2026-061035 BP787212026-05-132026-05-1302026
2026-009026 BP787042026-01-222026-01-2202026
2026-033453 BP787452026-03-112026-03-24132026
2026-045772 BP787222026-04-132026-04-1632026
2026-124989 BP787412026-09-212026-10-18272026
2026-121336 BP787272026-09-142026-09-1402026
2026-035500 BP787472026-03-232026-03-2522026
2025-139564 BP787532025-10-272025-11-17212025
2026-042615 BP786522026-04-072026-04-1472026
2026-001293 BP787312026-01-012026-01-0542026
2025-162876 BP787442025-12-182025-12-28102025
2026-136813 BP787232026-10-152026-10-1942026
2026-034841 BP787172026-03-222026-07-211212026
2026-019224 BP787482026-02-172026-02-2252026
2025-141822 BP787242025-10-272025-11-18222025
2025-163504 BP787562025-12-302025-12-3002025
2025-141872 BP787412025-11-022025-11-30282025
2026-117872 BP787232026-09-072026-09-0812026
2026-138927 BP787312026-10-202026-10-2002026
2026-058664 BP787582026-05-102026-05-1002026
2025-145529 BP787592025-11-112025-11-1102025
2026-030346 BP787442026-03-112026-07-261372026
2026-129628 BP787032026-09-302026-09-3002026
2026-029757 BP787302026-03-102026-03-1112026
2026-131360 BP787442026-10-052026-10-0502026
2026-032196 BP787562026-03-162026-03-1602026
2026-139897 BP787512026-10-222026-10-2202026
2026-108437 BP787482026-08-182026-08-1802026
2026-027646 BP787232026-03-052026-03-0942026
2025-136527 BP787592025-10-202025-11-04152025
2026-038707 BP787232026-03-232026-03-3072026
2026-066513 BP786602026-05-142026-07-14612026
2026-060225 BP787412026-05-122026-05-1202026
2026-109849 BP787472026-08-202026-08-2002026
2026-127230 BP787442026-09-272026-09-2702026
2026-089844 BP787502026-07-122026-08-16352026
2026-098348 BP787452026-07-282026-08-16192026
2026-060971 BP787172026-05-132026-05-1302026