How long does a interior alteration permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

3 calendar days

n = 2424 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 2424. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2026-068313 BP787462026-05-282026-06-0362026
2026-141993 BP787232026-10-262026-10-2602026
2025-147033 BP787032025-11-122025-11-1862025
2025-162547 BP787022025-12-172026-01-01152026
2026-111483 BP787042026-08-242026-08-2512026
2025-132773 BP787272025-10-122025-11-12312025
2026-036794 BP787492026-03-252026-03-2942026
2026-050195 BP787022026-04-222026-04-2422026
2025-156505 BP787412025-12-082025-12-1462025
2026-055880 BP787592026-05-042026-05-0512026
2025-138634 BP787532025-10-262025-12-04392025
2025-152969 BP787222025-12-012025-12-0102025
2026-042089 BP787582026-04-022026-04-0752026
2026-018783 BP787172026-02-162026-02-2262026
2026-023855 BP787212026-02-192026-02-2672026
2026-005788 BP787482026-01-142026-01-2062026
2026-114536 BP787502026-08-312026-10-14442026
2026-025682 BP787302026-03-022026-03-0862026
2025-143899 BP787442025-11-062025-11-0602025
2026-018731 BP787032026-02-162026-02-2262026
2026-028291 BP787392026-03-082026-03-23152026
2026-056636 BP787532026-05-052026-05-0612026
2025-163359 BP787472025-12-292026-01-0792026
2026-115541 BP787042026-09-012026-09-20192026
2025-162249 BP787532025-12-252025-12-2832025
2025-135884 BP787482025-10-192025-12-04462025
2025-154340 BP787292025-12-032025-12-0412025
2026-142281 BP787542026-10-272026-10-2702026
2026-093941 BP787392026-07-202026-07-2222026
2026-045732 BP787572026-04-132026-04-30172026
2026-003722 BP787172026-01-112026-02-10302026
2026-110549 BP787412026-08-192026-08-2342026
2026-069880 BP787222026-06-012026-06-0212026
2026-136873 BP787212026-10-152026-10-1832026
2026-012451 BP787542026-02-012026-02-0322026
2026-101521 BP787512026-08-042026-08-0512026
2026-123342 BP787482026-09-172026-10-05182026
2025-153372 BP787542025-12-012025-12-0212025
2026-046016 BP787502026-04-142026-04-1512026
2026-077278 BP787232026-06-162026-06-1602026
2026-086149 BP787442026-07-052026-07-0502026
2026-094459 BP787472026-07-212026-07-2212026
2025-146056 BP787302025-11-042025-12-10362025
2026-106361 BP787592026-08-132026-08-1302026
2026-128259 BP787592026-09-282026-10-20222026
2026-013095 BP787262026-02-022026-02-0312026
2026-022560 BP787502026-02-242026-02-2402026
2026-106614 BP787582026-08-132026-08-25122026
2026-091557 BP787532026-07-152026-07-1942026
2026-004591 BP787572026-01-122026-01-2192026

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.