How long does a interior alteration permit take in Austin?
Median application-to-issuance time
3 calendar days
n = 2424 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.
Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.
Explore the ZIP-level record
Records used in this calculation
Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 2424. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.
| Permit | ZIP | Applied | Issued | Calendar days | Source year |
|---|---|---|---|---|---|
| 2026-049238 BP | 78749 | 2026-04-20 | 2026-04-26 | 6 | 2026 |
| 2026-118314 BP | 78757 | 2026-09-03 | 2026-09-08 | 5 | 2026 |
| 2026-132717 BP | 78754 | 2026-10-07 | 2026-10-07 | 0 | 2026 |
| 2026-066431 BP | 78745 | 2026-05-25 | 2026-06-07 | 13 | 2026 |
| 2026-061121 BP | 78753 | 2026-05-13 | 2026-05-19 | 6 | 2026 |
| 2026-070033 BP | 78753 | 2026-06-01 | 2026-06-02 | 1 | 2026 |
| 2026-067384 BP | 78741 | 2026-05-27 | 2026-05-27 | 0 | 2026 |
| 2026-020756 BP | 78703 | 2026-02-19 | 2026-03-15 | 24 | 2026 |
| 2026-129061 BP | 78748 | 2026-09-29 | 2026-09-30 | 1 | 2026 |
| 2026-081300 BP | 78745 | 2026-06-14 | 2026-06-23 | 9 | 2026 |
| 2025-149378 BP | 78702 | 2025-11-19 | 2025-12-28 | 39 | 2025 |
| 2026-136634 BP | 78717 | 2026-10-15 | 2026-10-15 | 0 | 2026 |
| 2026-028676 BP | 78741 | 2026-03-08 | 2026-03-09 | 1 | 2026 |
| 2025-149155 BP | 78748 | 2025-11-18 | 2025-11-19 | 1 | 2025 |
| 2026-131125 BP | 78754 | 2026-10-05 | 2026-10-05 | 0 | 2026 |
| 2026-097716 BP | 78744 | 2026-07-21 | 2026-07-28 | 7 | 2026 |
| 2026-121225 BP | 78731 | 2026-09-14 | 2026-09-14 | 0 | 2026 |
| 2025-158823 BP | 78751 | 2025-12-14 | 2025-12-14 | 0 | 2025 |
| 2025-150515 BP | 78721 | 2025-11-16 | 2025-11-23 | 7 | 2025 |
| 2026-065309 BP | 78744 | 2026-05-21 | 2026-05-25 | 4 | 2026 |
| 2026-119032 BP | 78617 | 2026-09-09 | 2026-09-09 | 0 | 2026 |
| 2025-146468 BP | 78754 | 2025-11-12 | 2025-11-18 | 6 | 2025 |
| 2026-118655 BP | 78731 | 2026-09-08 | 2026-09-09 | 1 | 2026 |
| 2026-112531 BP | 78736 | 2026-08-26 | 2026-08-26 | 0 | 2026 |
| 2026-055472 BP | 78750 | 2026-05-03 | 2026-05-05 | 2 | 2026 |
| 2026-077958 BP | 78727 | 2026-06-14 | 2026-06-17 | 3 | 2026 |
| 2025-152035 BP | 78754 | 2025-11-25 | 2025-11-30 | 5 | 2025 |
| 2026-094441 BP | 78748 | 2026-07-21 | 2026-07-29 | 8 | 2026 |
| 2026-086698 BP | 78617 | 2026-07-06 | 2026-07-06 | 0 | 2026 |
| 2026-130037 BP | 78758 | 2026-10-01 | 2026-10-05 | 4 | 2026 |
| 2026-027233 BP | 78744 | 2026-03-05 | 2026-03-09 | 4 | 2026 |
| 2026-125438 BP | 78747 | 2026-09-22 | 2026-09-22 | 0 | 2026 |
| 2025-131849 BP | 78754 | 2025-10-09 | 2025-11-17 | 39 | 2025 |
| 2025-151983 BP | 78702 | 2025-11-25 | 2025-11-30 | 5 | 2025 |
| 2026-043603 BP | 78745 | 2026-04-08 | 2026-04-27 | 19 | 2026 |
| 2026-077317 BP | 78724 | 2026-06-16 | 2026-06-16 | 0 | 2026 |
| 2026-006343 BP | 78731 | 2026-01-15 | 2026-01-20 | 5 | 2026 |
| 2026-088101 BP | 78749 | 2026-07-08 | 2026-07-23 | 15 | 2026 |
| 2026-015955 BP | 78758 | 2026-02-09 | 2026-02-12 | 3 | 2026 |
| 2026-009643 BP | 78724 | 2026-01-25 | 2026-01-25 | 0 | 2026 |
| 2026-081770 BP | 78703 | 2026-06-24 | 2026-06-24 | 0 | 2026 |
| 2026-041991 BP | 78727 | 2026-04-06 | 2026-04-14 | 8 | 2026 |
| 2025-140952 BP | 78727 | 2025-10-30 | 2025-12-07 | 38 | 2025 |
| 2026-006314 BP | 78745 | 2026-01-15 | 2026-01-27 | 12 | 2026 |
| 2026-045041 BP | 78703 | 2026-04-08 | 2026-04-13 | 5 | 2026 |
| 2025-151377 BP | 78745 | 2025-11-24 | 2025-11-24 | 0 | 2025 |
| 2026-042910 BP | 78703 | 2026-04-07 | 2026-04-13 | 6 | 2026 |
| 2026-061088 BP | 78758 | 2026-05-13 | 2026-05-13 | 0 | 2026 |
| 2026-129977 BP | 78754 | 2026-10-01 | 2026-10-05 | 4 | 2026 |
| 2026-040185 BP | 78735 | 2026-03-29 | 2026-04-23 | 25 | 2026 |
PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.