AUSTIN · PERMIT TIMELINES

How long does a interior alteration permit take in Austin?

A historical population statistic from this registry. It does not predict an individual application or determine whether your project needs a permit.

Median application-to-issuance time

3 calendar days

n = 2424 usable timelines · Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026
As of 2026-11-03 (coverage endpoint). Issued-date window: 2025-11-03 through 2026-11-03, inclusive.

Recomputed from application and issuance dates in their configured source-field time zones. Missing or reversed dates and unsourced records are excluded. Pool/spa records are excluded by whole-word matching, including plurals, in project class and work description. Stored derived medians are not substituted.

All Austin project timelinesUnderlying recordsData & methodology

Explore the ZIP-level record

Records used in this calculation

Source: City of Austin Issued Construction Permits (Socrata 3syk-w9eu) · Source years: 2025, 2026 · As of 2026-11-03 · n = 2424. Dates below are calendar dates in the source fields’ configured time zones. No addresses or homeowner names are displayed.

PermitZIPAppliedIssuedCalendar daysSource year
2025-152862 BP787232025-12-012025-12-0102025
2025-148870 BP787412025-11-182025-11-1912025
2025-151645 BP787492025-11-242025-11-2512025
2026-142013 BP786602026-10-222026-10-2862026
2025-143242 BP787472025-11-052025-11-0612025
2026-068793 BP787452026-05-312026-06-0112026
2026-096539 BP787312026-07-162026-07-27112026
2026-054076 BP787472026-04-292026-05-19202026
2026-071012 BP787412026-06-032026-06-0852026
2026-073255 BP787242026-06-082026-06-0802026
2026-026638 BP787352026-03-042026-03-1062026
2026-105973 BP787022026-08-122026-08-1202026
2026-016082 BP787212026-02-022026-02-16142026
2025-152044 BP787242025-11-252025-11-3052025
2026-089013 BP787592026-07-052026-07-1492026
2025-148800 BP787472025-11-182025-11-1912025
2026-068151 BP787042026-05-282026-07-01342026
2025-145809 BP787022025-11-052025-11-23182025
2026-049638 BP787452026-04-212026-04-2652026
2025-129124 BP787532025-10-052025-11-17432025
2025-125014 BP787232025-09-302025-12-23842025
2026-112458 BP787472026-08-262026-08-2602026
2023-025088 BP787312023-03-012026-10-2613352026
2026-122639 BP787262026-09-162026-09-1712026
2026-024188 BP787572026-02-262026-03-0352026
2026-028994 BP787272026-03-092026-03-1012026
2026-105261 BP787512026-04-262026-09-071342026
2026-011396 BP787052026-01-292026-01-2902026
2026-008706 BP787442026-01-222026-02-08172026
2026-002667 BP787482026-01-072026-01-0812026
2025-150651 BP786172025-11-232025-11-2522025
2026-021702 BP787482026-02-162026-02-2482026
2026-020698 BP787532026-02-192026-03-15242026
2026-004617 BP787472026-01-122026-01-1312026
2026-022563 BP787442026-02-242026-02-2402026
2025-163689 BP787452025-12-302026-01-0122026
2026-044882 BP787482026-04-122026-04-1312026
2026-040463 BP787502026-04-022026-04-0752026
2026-133628 BP787522026-10-062026-10-17112026
2026-089966 BP787032026-07-122026-07-1312026
2026-139346 BP787472026-10-212026-10-2102026
2025-163720 BP787512025-12-302026-01-0122026
2025-152335 BP787482025-11-302025-11-3002025
2025-146784 BP787482025-11-132025-11-1412025
2025-159007 BP787442025-12-152025-12-30152025
2026-020363 BP787572026-02-112026-02-1982026
2025-151005 BP787482025-11-232025-11-2412025
2026-091734 BP787352026-07-152026-07-1502026
2025-154942 BP787542025-12-042025-12-0732025
2026-124479 BP787542026-09-212026-09-2432026

PermitLedger publishes public permit records and population-level statistics. It does not rule on permit requirements for any specific project, and a contractor's permit footprint is a public record, not a rating, license, or endorsement.